The main project of horizontal deplacement monitoring by geodetic methods at the area of 'Nova Kolubara'
Glavni projekat geodetskog osmatranja horizontalnog pomeranja priobalja reke 'Nova Kolubara'
Апстракт
The new position of the Kolubara river has been finished since 19.09.2007. Starting from that time, new works are oriented through finishing activities regarding to the new river flow. This article presents the geodetic methods of deformation analysis and explains the activities and contents of the new design of geodetic work which aims to monitoring of horizontal deplacement of the terrain around the area of the new river banks.
Osnovno korito novog toka Kolubare je završeno i u funkciji je od 19.09.2007. godine. Od dana usmeravanja toka u novoizgrađeno korito Kolubare, odvijaju se radovi na završetku regulacionih i zaptivnih radova i redovno kontrolišu efekti novog rešenja. Ovaj rad se bavi primenom geodetskih metoda merenja u praćenja pomeranja terena u zoni objekta. S obzirom na odluku rukovodstva površinskog kopa Kolubara da se buduća geodetska osmatranja moraju realizovati po unapred predviđenom planu opažanja i metodologiji, urađen je Glavni projekat geodetskog osmatranja u vertikalnoj i horizotalnoj ravni. Rad daje pregled dela Glavnog projekta koji se odnosi na definisanje postupaka i procedura u okviru geodetskog osmatranja horizontalnih pomeranja terena u zoni novog korita.
Кључне речи:
Surface mine Kolubara / Geodetic monitoring of horizontal deplacement / Main project / Površinski kop Kolubara / Geodetsko osmatranje horizontalnog pomeranja / Glavni projekatИзвор:
Tehnika - Naše građevinarstvo, 2010, 64, 4, 11-17Издавач:
- Savez inženjera i tehničara Srbije, Beograd
Институција/група
GraFarTY - JOUR AU - Božić, Branko AU - Ašanin, Slobodan AU - Gospavić, Zagorka AU - Milovanović, Branko PY - 2010 UR - https://grafar.grf.bg.ac.rs/handle/123456789/339 AB - The new position of the Kolubara river has been finished since 19.09.2007. Starting from that time, new works are oriented through finishing activities regarding to the new river flow. This article presents the geodetic methods of deformation analysis and explains the activities and contents of the new design of geodetic work which aims to monitoring of horizontal deplacement of the terrain around the area of the new river banks. AB - Osnovno korito novog toka Kolubare je završeno i u funkciji je od 19.09.2007. godine. Od dana usmeravanja toka u novoizgrađeno korito Kolubare, odvijaju se radovi na završetku regulacionih i zaptivnih radova i redovno kontrolišu efekti novog rešenja. Ovaj rad se bavi primenom geodetskih metoda merenja u praćenja pomeranja terena u zoni objekta. S obzirom na odluku rukovodstva površinskog kopa Kolubara da se buduća geodetska osmatranja moraju realizovati po unapred predviđenom planu opažanja i metodologiji, urađen je Glavni projekat geodetskog osmatranja u vertikalnoj i horizotalnoj ravni. Rad daje pregled dela Glavnog projekta koji se odnosi na definisanje postupaka i procedura u okviru geodetskog osmatranja horizontalnih pomeranja terena u zoni novog korita. PB - Savez inženjera i tehničara Srbije, Beograd T2 - Tehnika - Naše građevinarstvo T1 - The main project of horizontal deplacement monitoring by geodetic methods at the area of 'Nova Kolubara' T1 - Glavni projekat geodetskog osmatranja horizontalnog pomeranja priobalja reke 'Nova Kolubara' EP - 17 IS - 4 SP - 11 VL - 64 UR - https://hdl.handle.net/21.15107/rcub_grafar_339 ER -
@article{ author = "Božić, Branko and Ašanin, Slobodan and Gospavić, Zagorka and Milovanović, Branko", year = "2010", abstract = "The new position of the Kolubara river has been finished since 19.09.2007. Starting from that time, new works are oriented through finishing activities regarding to the new river flow. This article presents the geodetic methods of deformation analysis and explains the activities and contents of the new design of geodetic work which aims to monitoring of horizontal deplacement of the terrain around the area of the new river banks., Osnovno korito novog toka Kolubare je završeno i u funkciji je od 19.09.2007. godine. Od dana usmeravanja toka u novoizgrađeno korito Kolubare, odvijaju se radovi na završetku regulacionih i zaptivnih radova i redovno kontrolišu efekti novog rešenja. Ovaj rad se bavi primenom geodetskih metoda merenja u praćenja pomeranja terena u zoni objekta. S obzirom na odluku rukovodstva površinskog kopa Kolubara da se buduća geodetska osmatranja moraju realizovati po unapred predviđenom planu opažanja i metodologiji, urađen je Glavni projekat geodetskog osmatranja u vertikalnoj i horizotalnoj ravni. Rad daje pregled dela Glavnog projekta koji se odnosi na definisanje postupaka i procedura u okviru geodetskog osmatranja horizontalnih pomeranja terena u zoni novog korita.", publisher = "Savez inženjera i tehničara Srbije, Beograd", journal = "Tehnika - Naše građevinarstvo", title = "The main project of horizontal deplacement monitoring by geodetic methods at the area of 'Nova Kolubara', Glavni projekat geodetskog osmatranja horizontalnog pomeranja priobalja reke 'Nova Kolubara'", pages = "17-11", number = "4", volume = "64", url = "https://hdl.handle.net/21.15107/rcub_grafar_339" }
Božić, B., Ašanin, S., Gospavić, Z.,& Milovanović, B.. (2010). The main project of horizontal deplacement monitoring by geodetic methods at the area of 'Nova Kolubara'. in Tehnika - Naše građevinarstvo Savez inženjera i tehničara Srbije, Beograd., 64(4), 11-17. https://hdl.handle.net/21.15107/rcub_grafar_339
Božić B, Ašanin S, Gospavić Z, Milovanović B. The main project of horizontal deplacement monitoring by geodetic methods at the area of 'Nova Kolubara'. in Tehnika - Naše građevinarstvo. 2010;64(4):11-17. https://hdl.handle.net/21.15107/rcub_grafar_339 .
Božić, Branko, Ašanin, Slobodan, Gospavić, Zagorka, Milovanović, Branko, "The main project of horizontal deplacement monitoring by geodetic methods at the area of 'Nova Kolubara'" in Tehnika - Naše građevinarstvo, 64, no. 4 (2010):11-17, https://hdl.handle.net/21.15107/rcub_grafar_339 .