Work cycle based scheduling
Apstrakt
The paper proposes a new approach to short-term scheduling based on spatial and technological cycles, continuous crew flows and daily scheduling, named WCBS (Work Cycle Based Scheduling). Application of WCBS is shown on a case study of constructing seven multi-storey structures. It was concluded that WCBS helps overcome restrictions of existing approaches to micro scheduling (daily tasks and crew coordination), enhances the scheduling process and increases productivity of works.
Ključne reči:
short-term schedules / workflow / work cycle / productivityIzvor: