Structural monitoring of rebuilt telecommunication tower 'Avala' / Konstrukcijski monitoring obnovljenog telekomunikacionog tornja 'Avala'
(Udruženje inženjera građevinarstva, geotehnike, arhitekture i urbanista "Izgradnja", Beograd, 2009)
Paper presents application of long-term Structural Health Monitoring - SHM of the rebuilt TV tower 'Avala'. According the actual trends for improvement of maintenance serviceability, safety and durability, on this structure ...
Polyurethane foam acoustic insulation / Akustička izolacija na bazi poliuretanskih pena
(Udruženje inženjera građevinarstva, geotehnike, arhitekture i urbanista "Izgradnja", Beograd, 2009)
Polyurethane based products are often used in civil engineering. Apart to regular use of this material in thermal insulation purposes, polyurethane is widely used in field of acoustic insulation. Usage of modern ...
Productivity planning and control on construction projects / Planiranje i kontrola produktivnosti na građevinskim projektima
(Udruženje inženjera građevinarstva, geotehnike, arhitekture i urbanista "Izgradnja", Beograd, 2015)
In this paper, traditional as well as contemporary approaches to productivity planning and control are analyzed and potential improvements are suggested. A new approach is proposed. It is based on: applying separate measures ...
Implementing a detailed estimation model on housing project prefeasibility studies / Primena detaljnog modela procene za potrebe izrade predinvesticionih studija za projekte izgradnje stambeno-poslovnih objekata
(Udruženje inženjera građevinarstva, geotehnike, arhitekture i urbanista "Izgradnja", Beograd, 2010)
In this paper, a new approach is presented for the purpose of making prefeasibility studies. It is based on the detailed estimation of costs and durations even though there is no design present at the beginning of the ...
Superelevation ramp design / Prostorno oblikovanje rampe za nadvišenje spoljne šine
(Udruženje inženjera građevinarstva, geotehnike, arhitekture i urbanista "Izgradnja", Beograd, 2010)
This paper presents general criteria for deriving a geometric shape for the transition curve and superelevation ramp, based on kinematic analysis of railway vehicle movement. According to European standard (ENV 13803-1) ...
Eurocode 6: Masonry structures / Evrokod 6 - zidane konstrukcije
(Udruženje inženjera građevinarstva, geotehnike, arhitekture i urbanista "Izgradnja", Beograd, 2010)
A general concept of Eurocode 6 - Design of Masonry Structures, as European standard which deals with basic problems of masonry structures, is presented in this paper. Special attention is dedicated to Chapter 3 of the ...
Railway transport competitiveness - Ecological aspect
(Izgradnja, 2015)
Geometry of twisted surfaces applied on horizontal communications in architecture / Geometrija spiralnih površi primenjena na horizontalne komunikacije u arhitekturi
(Udruženje inženjera građevinarstva, geotehnike, arhitekture i urbanista "Izgradnja", Beograd, 2013)
Contemporary technologies and materials continuously challenge structural designers, as well as architects, to achieve unique applications of various geometric surfaces. Twisted structures are actual and numerous in building ...
Design of circular composite CFT columns according to Eurocode 4 / Analiza nosivosti kružnih CFT stubova prema Evrokodu 4
(Udruženje inženjera građevinarstva, geotehnike, arhitekture i urbanista "Izgradnja", Beograd, 2013)
This paper presents a simplified method for calculation of bearing capacity of composite columns according to the European standard for the calculation of composite steel and concrete structures - Eurocode 4. Resistance ...
Metodology for construction equipment expense calculations used by the USACE / Metodologija proračuna troškova rada građevinskih mašina prema USACE
(Udruženje inženjera građevinarstva, geotehnike, arhitekture i urbanista "Izgradnja", Beograd, 2011)
Estimating expenses for Construction Equipment (CE) has a key impact on the success of civil engineering projects. The nature of these expenses is such that there is a need for a lot of assumptions during the estimating ...